Nigeria- Siemens Presidential Power Initiative (PPI) Phase 1, Batch 1—
2: Ayede–Ibadan, Oyo State — 330/132/33kV
-(a): Offa, Kwara State — 132/33kV
-(b): Onitsha, Anambra State — 330/132/33kV
-(c): Sokoto, Sokoto State — 132/33kV
-(d): Abeokuta, Ogun State — 330/132/33kV
3: These five are the Phase 1, Batch 1 substations approved by the Federal Executive Council, with a combined expected impact of about 986MW.
4: There is also the earlier Pilot Phase
-(a): The Siemens PPI pilot phase involved mobile substations/transformers at several existing transmission locations, including:
-(b) Apo, Abuja
Ajah, Lagos
Maryland, Lagos
Ojo, Lagos
Okene, Kogi
Amukpe, Delta
Ihovbor, Edo
Potiskum, Yobe
Birnin Kebbi, Kebbi
Kwanar Dangora, Kano
Jebba, among others.
5: Batch 2 is much larger: it is planned to comprise 6 brownfield and 10 greenfield substations, with a projected 4,104MW impact.
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
| |
| |
|
|
|
|
|